"The cost savings have been dramatic. Thanks to HVAC
improvements we're seeing a 42 percent reduction in natural
gas usage. And lighting upgrades have resulted in a significant
reduction in electrical consumption while increasing light
levels and quality."
- J. Dale Chaplow, Site Utility Manager - GM Oshawa
As the largest automotive facility in North
America, the GM Campus in Oshawa is
massive. And so was its potential for energy
savings. Through an in-depth assessment of
the 12-million square foot facility, Toronto
Hydro Energy Services, working with U.S.-
based energy management firm The Benham
Companies LLC, was able to uncover the
opportunity for an estimated $1.75 million
in annual utility savings. The challenge was
to implement the improvements without
affecting production in a plant where most
of the facility operates around the clock.
Downtime not an option
“This project was part of a North Americanwide
focus by General Motors on generating
cost savings through energy efficiency and
modeled after similar initiatives already
completed in the U.S. The goal was to realize
additional cash flow resulting from energy
savings. Production downtime was not an
option,” explains Dale Chaplow, who is the
Site Utility Manager at GM in Oshawa.
The project, which was projected to cost
$5 million, was partially completed during a
planned two-week vacation shutdown in July.
The remaining work was scheduled over
weekends and during regular production
periods in a manner that would not impair
plant operation. Toronto Hydro Energy
Services spearheaded the energy-efficient
lighting upgrades and provided support services
to Benham for the HVAC improvements.
Upgrading to energy-efficient lighting
Lighting levels are extremely important
to the tasks performed in the car and truck
assemblies and the stamping plant. Proposed
energy efficiency upgrades were designed to
deliver the necessary lighting levels while
lowering energy consumption. Newer, energyefficient
T8 fluorescent fixtures, which use
electronic ballasts, were installed to replace
2,500 existing T12 lighting fixtures in the
main assembly areas and the stamping facility.
In addition, a further 1,500 fixtures were
retrofitted with electronic ballasts and more
efficient T8 fluorescent lamps.
Targeted elimination of energy waste
Toronto Hydro Energy Services assessment
of the facility found that a significant number
of High Intensity Discharge fixtures at the
ceiling level that weren't necessary and often
interfered with the delivery of task lighting.
More than 600 ceiling lights were turned off
with no affect on lighting performance in the
production areas. Further savings were
realized by using sensors to regulate lighting
in mechanical areas and plant offices where
lighting could be turned on and off based on
occupancy.
Fine-tuning air intake
During heating season, bringing in cold,
outside air can have a sizeable impact on
heating costs. Yet the nature of the work
performed at GM requires a certain level of
air intake to meet exhaust requirements.
Controls were introduced to automatically
regulate air intake to match exhaust
requirements in order to maintain building
air balance. The controls also provide the
ability to shut fans off when the plant closes
down. In addition, several Air Supply Houses,
which heat the fresh air on intake, were
changed from indirect to direct-fired gas
heaters improving energy efficiency from
75% to over 90%.
Project fully completed in nine months
From initial assessment to implementation,
the extensive project was completed in just
nine months and costs came it at $4-million
- significantly less than estimated. Financing
was designed to use the $1.75 million in
annual utility savings to provide positive
cash flow to GM.
Toronto Hydro Energy Services was
selected to partner with Benham on the
GM - Oshawa project because of its
experience and recognized expertise in
this area, local presence and in-depth
knowledge of the GM facility and operating
environment. As Dale remarks, “We have
a complex, highly-tuned operation and
scheduling the project presented a number
of challenges. But Toronto Hydro Energy
Services showed that they knew their way
around the shop floor and were sensitive
to our safety requirements and collective
agreements, ensuring the project came in
on time and under budget.
|